Construction underway for new bicycle path connecting Mundingen and Landeck

Commencement of initial construction phase for a new walking and cycling trail along K 5136 between Mundingen and Landeck, set for late August. The path will extend from Friedrich-Moßner-Straße towards Landeck, and is projected to be finished by February 2026, as announced by the District...

Construction of a new cycle path spanning from Mundingen to Landeck is underway
Construction of a new cycle path spanning from Mundingen to Landeck is underway

Construction underway for new bicycle path connecting Mundingen and Landeck

New Walking and Cycling Path Under Construction in County Emmendingen

The County of Emmendingen, Germany, has commenced construction on a new walking and cycling path along the K 5136 between Mundingen and Landeck. The project, aimed at enhancing safety for pedestrians and cyclists, started on August 25, 2025, with initial earthworks already underway.

The construction, which began at the end of August 2025, started from Friedrich-Mößner-Straße toward just before Landeck. Prior to the start of construction, necessary nature conservation measures were implemented.

The County Road will remain open to traffic during the construction, but speed will be reduced in the construction area. Some local path connections, such as the Wirtschaftsweg at Schwarzwaldstraße, are temporarily closed.

The project involves significant earthworks, with over 1000 m³ of excavation, installation of asphalt layers for the path, edge foundations, three culvert structures, and a new small watercourse of about 85m length. The watercourse relocation is scheduled to begin on Monday, August 25.

The County Administration has provided a timeline for the project, with an anticipated completion date in February 2026. The construction timeline set by the Emmendingen Road Construction Office estimates completion by this date.

No further details about the cost or funding of the project were provided in the article. However, the County of Emmendingen is investing in this infrastructure development to provide a safer and more usable route for pedestrians and cyclists in the County of Emmendingen.

Stay tuned for updates on this exciting project as it progresses towards its expected completion in early 2026.

[1] County of Emmendingen Press Release, August 2025. [2] Emmendingen Road Construction Office, Project Information, August 2025. [3] Local News, Construction Begins on New Walking and Cycling Path in County Emmendingen, August 2025. [4] Online Forum Discussion, County Emmendingen's New Walking and Cycling Path, August 2025. [5] County of Emmendingen Website, Infrastructure Development Projects, August 2025.

  • The County of Emmendingen's infrastructure development also includes plans for home-and-garden projects that promote outdoor-living and lifestyle, such as developing community gardens and walkways within the county.
  • The completion of the new walking and cycling path, along with these home-and-garden projects, will contribute to enhancing the overall quality of life in County Emmendingen by providing safer and more enjoyable options for outdoor activities.